Question 1 of 10

1. X bar and S chart are more accurate in predicting out-of-control situations than the x bar and R charts, in the case of high sample size.

Question 1 of 10

Question 2 of 10

2. The value of L=3 in the genera model of control limits for a Shewhart control chart, explains ____________

Question 2 of 10

Question 3 of 10

3. The approximate upper control limit calculated for control chart limits based on an average sample size, is expressed by _____

Question 3 of 10

Question 4 of 10

4. If a process is out of control, what will be its ARL for the fraction nonconforming chart?

Question 4 of 10

Question 5 of 10

5. Which of these is true?

Question 5 of 10

Question 6 of 10

6. For what value of sample size, will the p-chart will have a LCL value higher than 0 when p=0.05 and 3 sigma limits are used?

Question 6 of 10

Question 7 of 10

7. We cannot analyze abnormal runs or patterns directly, on p-chart with variable sample size.

Question 7 of 10

Question 8 of 10

8. The gap between the UCL and LCL is double the gap between either one of them and the Center line, for the standardized chart.

Question 8 of 10

Question 9 of 10

9. In the case of automatic manufacturing, the sample size is ___________

Question 9 of 10

Question 10 of 10

10. For LCL for the p-chart to be higher than zero, what condition should the sample size fulfill?

Question 10 of 10


 

Manish Bhojasia - Founder & CTO at Sanfoundry
Manish Bhojasia, a technology veteran with 20+ years @ Cisco & Wipro, is Founder and CTO at Sanfoundry. He lives in Bangalore, and focuses on development of Linux Kernel, SAN Technologies, Advanced C, Data Structures & Alogrithms. Stay connected with him at LinkedIn.

Subscribe to his free Masterclasses at Youtube & discussions at Telegram SanfoundryClasses.